The Link River Dam is a concrete gravity dam on the Link River in the city of Klamath Falls, Oregon, United States. It was built in 1921 by the California Oregon Power Company (COPCO), the predecessor of PacifiCorp, which continues to operate the dam. The dam is owned by the U.S. Bureau of Reclamation. Link River Dam's reservoir, Klamath Lake, has a capacity of 873,000 acre-feet (1.077×109 m3). The project provides flood control, generates hydro power, and stores most of the water used for irrigation in the Klamath Reclamation Project. The dam is 22 feet (7 m) high and 435 feet (133 m) long.
rdf:langString
rdf:langString
Link River Dam
rdf:langString
Link River Dam
rdf:langString
Link River Dam
xsd:float
42.23389053344727
xsd:float
-121.8019409179688
xsd:integer
2969260
xsd:integer
1102800268
rdf:langString
The Link River Dam complex
xsd:date
1921-10-29
xsd:string
42.23388888888889 -121.80194444444444
rdf:langString
The Link River Dam is a concrete gravity dam on the Link River in the city of Klamath Falls, Oregon, United States. It was built in 1921 by the California Oregon Power Company (COPCO), the predecessor of PacifiCorp, which continues to operate the dam. The dam is owned by the U.S. Bureau of Reclamation. Link River Dam's reservoir, Klamath Lake, has a capacity of 873,000 acre-feet (1.077×109 m3). The project provides flood control, generates hydro power, and stores most of the water used for irrigation in the Klamath Reclamation Project. The dam is 22 feet (7 m) high and 435 feet (133 m) long. Its two channels can allow one outflow of 3,000 ft³/s (85 m³/s) with 1,000 ft³/s (28 m³/s) through the Ankeny Canal, and another outflow of 290 ft³/s (8 m³/s) through the Keno Canal. Those channels feed PacifiCorp's two hydroelectric turbines located downstream and generate 151 MW. All the flow is ultimately diverted down the Link River into Lake Ewauna. In 2004 PacifiCorp announced the Link River power projects would be abandoned, as the cost to repair the canal and pipeline supplying the power turbines is too high to be economically viable. As of 2014 the company intends to continue to run the plant, in the short term and at reduced output.
xsd:date
1920-07-29
<megawatt>
151.0
xsd:integer
2
xsd:gYear
1920
<kilometre>
0.113
xsd:nonNegativeInteger
7119
xsd:string
July 29, 1920
rdf:langString
Gravity dam
xsd:double
7.0
xsd:double
113.0
xsd:date
1921-10-29