Koldam Dam

http://dbpedia.org/resource/Koldam_Dam an entity of type: Thing

Das Koldam-Wasserkraftprojekt der indischen , kurz KolDam, ist eine in Bau befindliche Talsperre am Satluj bei Barmana am Chandigarh-Manali-Highway (NH-21) im Distrikt Bilaspur des indischen Bundesstaates Himachal Pradesh. Im Wasserkraftwerk gibt es 4 × 200 MW-Francis-Turbinen.Die hydraulische Fallhöhe beträgt 144 m. Die Hochwasserentlastung hat sechs Öffnungen. Der Stausee trägt den Namen Sundernagar-See. rdf:langString
The Koldam Hydropower Station commonly known as Koldam, is an embankment dam on the Sutlej River upstream of the Dehar Power House. It is 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana, Himachal Pradesh, India. The main purpose of the dam is hydroelectric power generation and it will support an 800 MW power station. The dam was constructed by NTPC Limited (erstwhile National Thermal Power Corporation Limited). rdf:langString
rdf:langString Koldam-Talsperre
rdf:langString Koldam Dam
rdf:langString Koldam
rdf:langString Koldam Hydro Power Station
rdf:langString thumb|Power House at the toe of the dam.
rdf:langString Koldam
xsd:float 31.38305473327637
xsd:float 76.87110900878906
xsd:integer 33848224
xsd:integer 1122241036
rdf:langString Chute with flip bucket, six radial gates
rdf:langString India
rdf:langString A rendition of the dam
rdf:langString India
xsd:integer 2015
rdf:langString O
xsd:string 31.383055555555554 76.8711111111111
rdf:langString Das Koldam-Wasserkraftprojekt der indischen , kurz KolDam, ist eine in Bau befindliche Talsperre am Satluj bei Barmana am Chandigarh-Manali-Highway (NH-21) im Distrikt Bilaspur des indischen Bundesstaates Himachal Pradesh. Der Hauptzweck der Talsperre ist Wasserkraftgewinnung. Sie erhält ein Kraftwerk mit 800 MW. Der Grundstein für den Staudamm wurde am 5. Juni 2000 von Premierminister Atal Bihari Vajpayee gelegt. Am 14. Januar 2004 begannen die Hauptarbeiten an dem Bauwerk. Wegen Umweltproblemen und Waldverlusten verzögerte sich das Projekt.Die Inbetriebnahme der Generatoren war erst für 2009 geplant und wurde auf 2013 verschoben. Das Bauwerk wurde 2013 bis auf Restarbeiten fertiggestellt. Seit Ende 2013 wird eingestaut, wobei es wiederum Verzögerungen gab. Die offizielle Einweihung wird 2015 stattfinden. Im Wasserkraftwerk gibt es 4 × 200 MW-Francis-Turbinen.Die hydraulische Fallhöhe beträgt 144 m. Die Hochwasserentlastung hat sechs Öffnungen. Der Stausee trägt den Namen Sundernagar-See.
rdf:langString The Koldam Hydropower Station commonly known as Koldam, is an embankment dam on the Sutlej River upstream of the Dehar Power House. It is 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana, Himachal Pradesh, India. The main purpose of the dam is hydroelectric power generation and it will support an 800 MW power station. The dam was constructed by NTPC Limited (erstwhile National Thermal Power Corporation Limited). Koldam project was first conceived in mid‐sixties and investigations on various possible sites had been in progress since 1966. Based on investigation carried out until 1975, a project report was prepared which envisaged construction of rockfill dam having an installed capacity of 600 MW. The work of investigation and studies was taken by HPSEB in October, 1984. The project capacity was revised to 800 MW, but work did not start for lack of funds. Subsequently, Koldam Hydro Project was taken over by NTPC in 2000 and Project Report was revised with a 167m high rock fill dam and Surface Power House located at toe of the dam with installed capacity of 4X200 MW. The foundation stone for the dam was laid on 5 June 2000 by Prime Minister Atal Bihari Vajpayee. On 14 January 2004, main construction on the dam began. KB Dubey was the first Head of the Project (BUH) . The current BUH is NS Thakur (since 2020). Due to problems associated with geological issues and declaration of part of reservoir area in 2006 as extension of Majathal Wildlife Sanctuary, the project got delayed. Attempts to impound the reservoir first failed in December 2013 due to problems with sealing the diversion tunnels. By 18 March 2014, a fourth attempt to seal the tunnels and fill the lake was underway. Repairs were made and another unsuccessful impounding was reached in April 2014 as the diversion tunnel continued to leak. Another period of impounding began on 3 November 2014 and finished on 3 January 2015. A tunnel still leaked though but authorities were confident they would have the power station operational by April. Generator commissioning was originally scheduled for 2009 but was rescheduled to 2015.
xsd:integer 2004
rdf:langString Sutlej
rdf:langString Embankment, rock-fill with clay core
rdf:langString 768.97 m
rdf:langString Koldam Hydro Power Station thumb|Power House at the toe of the dam.
xsd:decimal 3055000000
<megawatt> 800.0
xsd:double 43.58
xsd:integer 2015
xsd:integer 4
xsd:integer 90
xsd:integer 486
xsd:integer 53770
xsd:double 12.5
xsd:gYear 2004
<kilometre> 0.474
xsd:nonNegativeInteger 9089
xsd:string 2004
rdf:langString Embankment, rock-fill with clay core
xsd:double 648.0
xsd:double 474.0
xsd:gYear 2015
xsd:string O
xsd:double 12000000.0
<Geometry> POINT(76.871109008789 31.383054733276)

data from the linked data cloud